MAJORResolved
Data Center Power Outage — 23-24 July 2026
Started 4 months ago · Resolved 4 months ago
Affected components
Handling stages and targets
- Investigating24 Jul 2026, 07:54 WITA
- Identifiednot recorded
- Monitoringnot recorded
- Resolved24 Jul 2026, 11:31 WITA
| Initial response | 6 d 7 h | target ≤ 30 min | Missed |
| Recovery | 3 h 37 min | target ≤ 8 h | Met |
Initial response = the first update from the NOC after the outage was detected. An outage that recovered before the initial-response limit counts as handled. Targets follow severity: Critical ≤ 15 min/≤ 4 h, Major ≤ 30 min/≤ 8 h, Minor ≤ 1 h/≤ 24 h.
Timeline
- Resolved4 months ago
A power supply failure in the server room made every service and the network infrastructure unreachable for approximately 3 hours 37 minutes (24 July 07:54 - 11:31 WITA). The technical team completed recovery and all services are operating normally again.